storm Friday, roof and detail work
After setting up with huge advances - so for the layman observer at least - we went on Thursday and Friday mainly on the roof on. Tarpaulins, battens and now the Vitosol solar system were installed.
Carsten could dig after 3 days and finally expose the ends of the conduits for the utilities (one for 100 water, two 50's for Stom and phone) and find the tubes of the multi-branch Hauff introduction. Not without difficulty - with a skeleton arm fell off the foot after it long enough including gravel had been removed. Was to be expected due to gravity, but a surprising end yet. But thanks to the namesake of professional support, was the corner with an entrance hall are again supported. Now the city works to come early next week and connect power / phone (Monday), and water (Tuesday).
works in contrast to the one or the other builders in our communication with their leaders so far fine. Work is also done at short notice and arrangements maintained.
We have chosen the way that set the city works a temporary connection in the laundry room with a 32 A fuse, first, to enable then enough juice for the screed machine is there and we secondly, in comparison with the site electricity low rates are. The latest on the floor so that makes drying it out a lot. Let's hope.
We have today made from all rooms pictures, so thanks to the (up to two rooms) open ceiling, hopefully, you can find the cable run, but later when we have to drill again. However, this is probably an optimistic undertaking, if the "cable-highways" as seen in the living room Sun But pictures at least not hurt and it was done relatively quickly.
morning we will cancel the utility room before, because otherwise we may get no more, when the heat pump is in place. Let's see if we won the later nor can render.
We got the party ever the key. Our first house keys - a nice feeling!
announced Thursday was mainly roof battens
The introduction of multi-branch dug behind the wooden boards. After the 4 tubes have not shown the same, Carson had to dig below the bottom plate with his hand and then continue to the upper end down. It then fell off the visible part of the framework and foot beam. But well that ends well ... now, we could also use the corner but still nen basement. Mmm ...
One of our cable car tracks ...
end of the day on Thursday
lifted on Friday morning, another crane the bricks and the roof Vitosol.